Nam Ngum III and IV
 hydropower development projects

 (Laos)



















































          Client: Électricité du Laos (EDL)
          Assignment: Assistance to the Owner, technical expertise, construction supervision
          Aim: Construction of hydroelectric assemblies (dam, underground structures, power plant and transmission line) for Nam Ngum III (480 MW) and  Nam Ngum IV (240 MW)
          Dates: 2017-2023